Confidential Commercial Client

Newark, New Jersey

Scope of Service: Site Remediation, Brownfield Redevelopment

Site Remediation

Project involved the removal of 60,000 tons of soils impacted by PAHs, arsenic and lead. An additional 8,000 tons of construction debris were excavated and removed. Total depth of the excavation ranged from 14 to 18 feet below grade surface, and required sloping of the sidewalls. Approximatly 100 feet of sheet piling was used to provide adequate shoring of the excavation. Excavation was lined with stone and geotech fabric and backfilled and compacted in compliance with strict engineering guidelines.